Problem 21-11
Assume that Product Z is made of two units of A and four units of B. A is made of three units of C and three of D. D is made of three units of E. |
Lead times for purchase or fabrication of each unit to final assembly are: Z takes two weeks; A, B, C, and D take one week each; and E takes three weeks. |
Seventy units OF Product Z are required in Period 10. (Assume that there is currently no inventory on hand of any of these items.) |
b. |
Develop an MRP planning schedule showing gross and net requirements and order release and order receipt dates. (Leave no cells blank – be certain to enter “0” wherever required.)
Problem 21-18
|